✓ Completed
2025
Design
March 2026 to December 2026
Construction
To replace key equipment to improve performance and maintenance access.
Location
Lincoln
Status
Active construction
Timeline
2025 - December 2026
The Jordan Valley Sewage Pumping Station was built in 1976 and updated in 2015. It is located at 3850 Twenty-First St. in Lincoln.
Based on the 2021 Master Servicing Plan, this station does not need a capacity upgrade. However, it is not meeting its approved rated capacity of 40 litres per second, so the pumps need to be replaced.
Work includes:
Stephan Gazzola
Project Manager
Niagara Region
905-933-8526
Email Stephan Gazzola
Andrew Flagg
Project Manager
R.V. Anderson
905-685-5049 ext. 4206
Email Andrew Flagg