St. Paul Street Bridge: landscaping (weather permitting)
St. Paul Street Bridge: electrical, railings and final concrete (weather permitting).
We’ve redesigned niagararegion.ca to make it easier to find what you need. During this transition, search is still learning and some pages may have a new home. If you don’t find what you’re looking for, try browsing by topic from the main menu or visit our sitemap.
Plan, design and replace the CN Rail bridge on St. Paul Street West (Regional Road 81).
Location
St. Catharines
Status
Active construction
Timeline
February 2019 - Spring 2026
The Go Station Precinct project combines the scope of work of four projects that Niagara Region and the City of St. Catharines are working on.
The works as part of the overall project include:
These projects have been grouped for faster and more efficient construction. Separately, they would take up to seven years to complete. By combining them under one project, they are expected to be done within three years.
Niagara Region is leading the project because of its close relation to the St. Catharines Train Station redevelopment to a multi-model transit hub. Improvements to access the transit station via Great Western Street will be addressed.
Niagara Region completed a Municipal Class Environmental Assessment to replace the St. Paul Street West CN Rail Bridge in St. Catharines. The bridge was originally built in 1922. It has undergone extensive inspection and evaluation showing it needed immediate replacement.
Load restrictions and lane closures were put in place in December 2022 due to its condition. In November 2023, Niagara Region and Canadian National Railway closed the bridge to all vehicles. This was due to the continuing deterioration of the structure and the significant risk to the health and safety of the public.
The replacement will address the aging infrastructure. It will also improve the roadway's vertical alignment and the retaining walls on all bridge approaches.
The Region has worked with the bridge owner, Canadian National Railway, and Bell Canada to have their utilities removed. Bell completed this work in September 2024. In November 2024, the existing bridge was dismantled and removed, followed by construction of the new bridge.
Work to construct the bridge has been prioritized for completion within the overall project. It is expected to reopen to one-way traffic by the end of December 2025.
Currently, there are no impacts to pedestrian and vehicular traffic on St. Paul Street West and to the GO Precinct development.
Project File Report
Public open house - Nov. 8, 2023
Public open house - Sept. 25, 2024
Mike Wilson, A.Sc.T., PMP
Manager, Capital Projects, Transportation Engineering
Niagara Region
905-980-6000 ext. 3183
Email Mike Wilson