Bridge and Road Reconstruction of Niagara Street (Regional Road 50) from Riverbank Street to West Main Street
All Niagara Region projects

About the project

The Niagara Street bridge in Welland carries vehicular and pedestrian traffic along Niagara Street (Regional Road 50) over the Welland River.

This project includes:

  • Replacing the Niagara Street Bridge
  • Reconstructing the road between Riverbank Street and West Main Street
  • A new water transmission main from Riverbank Street to Mill Street
  • A new watermain and sanitary sewer from West Main Street to Mill Street

The project includes the following active transportation improvements:

  • 1.8-metre sidewalks on both sides of the bridge
  • Extending the southbound bike lane from Riverbank Street to Bald Street to connect to the existing bike network
  • Extending the northbound bike lane from Riverbank Street to Mill Street

On-street parking on the northbound side of the road from Mill Street to West Main Street will remain.

Project timeline

September 2019 - completed
Notice of study commencement

2019 - completed
Design of interim repairs

january 2019 - completed
Interim construction repairs

december 2020 - completed
Environmental assessment - Schedule "C" for bridge replacement and watermain extension

march 4, 2021 - completed
Public Information Centre #1

June 21 to July 2, 2021 - completed
Public Information Centre #2

2022 - completed
Schedule C Environmental Assessment and Environmental Study Report

May 2025 - completed
Repair sidewalk

Spring 2026
Start detailed design

Fall 2027
Pre-construction information meeting

Spring 2028
Start construction

Contact

Carolyn Rodgers
Senior Project Manager, Transportation Engineering
Niagara Region
905-980-6000 ext. 3192
Email Carolyn Rodgers