During the last upgrade, it was noted that structural improvements would be required to retain the integrity of the roof of the settling tank in Plant 1. As part of the preliminary design assignment, an assessment of the tank was undertaken and it was determined that rehabilitation was required to extend the life of the structure.
Establishment of the project is being conducted in accordance with the approved requirements of Schedule 'A+', as defined in the Municipal Engineers Association Class Environmental Assessment document (2007). Schedule 'A+' projects are pre-approved. This notice satisfies the Class EA process requiring public notification before proceeding with the proposed works.
For further information on this project or to review a copy of the Municipal Class Environmental Assessment document please contact one of the following:
|
Mr. Tony Cimino, C.E.T. |
Mr. Gus Proietti, P. Eng. |