Reconstruction of Bridge Street (Regional Road 43) and Victoria Avenue into a Roundabout (Phase 2, Stage 1), and Thorold Stone Road (Regional Road 57) Extension from Limit to Roundabout (Phase 2, Stage 2)
All Niagara Region projects

About the project

Niagara Region is extending Thorold Stone Road (Regional Road 57) where it currently ends at the Gale Centre entrance (Phase 1) to the Victoria Avenue and Bridge Street (Regional Road 43) intersection with a roundabout (Phase 2).

The extension will provide:

  • A key connection to the QEW
  • An improved east / west linkage to the City of Niagara Falls' downtown area and Niagara River Parkway
  • Economic growth and redevelopment of a significant brownfield for the City of Niagara Falls

With improved transportation connectivity and daily GO train service to Niagara Falls by 2023, there's an opportunity to leverage and enhance the land uses. This will ensure it's an attractive arrival point for commuters and visitors.

Niagara Region is working with the City of Niagara Falls to determine a vision for the GO Station area. This includes road, transit, public realm and active transportation options for the Bridge Street / GO Station area as identified in the approved Niagara Falls Transit Station Secondary Plan.

Construction of the roundabout is now complete. The extension of the Thorold Stone Road (Regional Road 57) project is targeted for construction commencement in 2024.

Complete Streets

We'll integrate design elements that support the Complete Streets Design Guidelines for Niagara. The guidelines will focus on enhancing the functionality of boulevards and roadway safety.

The goal is to provide an innovative and creative solution that is:

  • Environmentally sustainable
  • Attracts growth on adjacent lands
  • Supports active transportation and other modes of mobility to help people of all ages travel throughout Niagara

Project timeline

april 2021 - completed
Start utility relocations

December 2021 - completed
Public Information Centre #1

Winter 2021 - completed
Complete utility relocations

Winter 2021 - completed
Roundabout tender closes

Winter / Spring 2022 - completed
Start roundabout construction

Summer 2022 - completed
Complete roundabout construction

Fall / Winter 2024
Construction of Thorold Stone Road extension commences (pending budget approval)

Contact

Stephanie Huppunen
Manager, Capital Projects Transportation Engineering
Niagara Region
905-980-6000 ext. 3552
Email Stephanie Huppunen

Image Gallery


01 January 2022

Reports and Documents

Public Information Centre #1 - December 2021

Page Feedback Did you find what you were looking for today?