Stamford Interceptor Trunk Sewer Rehabilitation - Phase II
All Niagara Region projects

About the Project

The Stamford interceptor trunk sewer is located in Niagara Falls and runs parallel to the Ontario Power Generation hydro canal from Dorchester Road to the Niagara Falls Wastewater Treatment Plant at 3450 Stanley Avenue.

Niagara Region's inspection program identified a number of sewers and maintenance holes in the Stamford interceptor trunk sewer that are corroded and in need of rehabilitation.

Phase II of the project includes the rehabilitation of 14 sewer sections and 13 maintenance holes spanning approximately 1,560 metres in length. The section of sewer requiring the work travels parallel to the Ontario Power Generation canal, starting at the Millennium Recreational Trail, approximately 450 metres south of Thorold Stone Road to the Niagara Falls Wastewater Treatment Plant.

Project Timeline

July 26, 2021 - completed
Construction starts

December 2021
Complete construction

Contact

Derek Falardeau-Mercier, P.Eng.
Niagara Region
Senior Technical Project Manager
905-980-6000 ext. 3205
Email Derek Falardeau-Mercier

Joe Linseman, P.Eng.
Robinson Consultants
Senior Project Manager
905-304-0080 ext. 236
jlinseman@rcii.com

Local Information

The Millennium Trail between Thorold Stone Road to 500 metres northeast of Portage Road is closed until Dec. 17 to maintain health and safety during construction.

Image Gallery


Stamford1
Work being done at the Stamford interceptor trunk sewer.

Map of the Millenium recreational trail closure. The trail is closed from August 3 to November 30 from the on ramp from Thorold Stone Road to just before Portage Road and Althea

street.

Page Feedback Did you find what you were looking for today?