The reconstruction of Ontario Street (Regional Road 42) between Linwell Road and Lakeport Road (Regional Road 87) will be completed as part of a Municipal Class Schedule "C" Environmental Assessment, which identified the need for improvement in traffic operations, capacity and safety, all of which will be addressed.

The work to be completed includes the reconstruction and widening of the intersection, installation of a new storm sewer and culvert replacement, upgraded illumination and inclusion of active transportation. Sidewalk upgrades and watermain work will also be completed on behalf of the City of St. Catharines.

Project Timeline

february 2021 - completed
Syphon investigation and clean out

Spring 2022 - completed
Subsurface Utility Engineering Level A investigations start

Winter 2022 - Completed
Tree removals

Winter 2022 - Completed
Water service extensions (Lakehurst to Chapleau)

Winter 2022 - completed
Start utility relocations

Spring to Summer 2022 - completed
Finish utility relocations

january 2023 - Completed
Issue tender for construction (pending budget approval)

June 1, 2023
Public Information Centre #1

Summer 2023
Start construction

Summer 2024
Pause construction for the World Rowing Championships

Late summer 2024
Start construction again

summer 2024
Finish construction

Contact

Stephanie Huppunen
Manager, Capital Projects Transportation Engineering
905-980-6000
Email Stephanie Huppunen

Local Information

Businesses remain open

Temporary lane, sidewalk and driveway closures may happen from time to time, but access to businesses will be maintained at all times.

Expected traffic delays

Regional traffic will be kept open to through traffic during construction. However, throughout construction there will be temporary lane restrictions which will result in delays. Drivers can avoid delays by using alternative routes.

Public Information Centre #1

Thursday, June 1 from 3:30 - 7:30 p.m.
Bill Burgoyne Memorial Arena
129 Linwell Rd., St. Catharines

Join the Public Information Centre to learn about the planned construction and community improvements.

Image Gallery


Regional Rd 42
This map shows the construction area on Ontario Street (Regional Road 42).
This image shows the area that will be reconstructed on Ontario Street (Regional Road 42) between Linwell Road and Lakeport Road (Regional Road 87).
Page Feedback Did you find what you were looking for today?