Portage Trunk Sewer Rehabilitation
All Niagara Region projects
About the project
Niagara Region has started the preliminary and detailed design for improvements to the Portage Trunk Sewer in Niagara Falls. The sewer is in poor condition and needs repair.
The sewer is located along a hydro corridor between the rear yards of Sheldon Street and Darcy Crescent / Maplewood Avenue. Sewage from the Kalar Road Sewage Pumping Station flows into the trunk sewer at an access point. This access point is south of the rear fence line at 6606 Sheldon Ave. The sewer continues east for about 1.3 kilometres before discharging to the Stamford Interceptor. It then finally reaches the Niagara Falls Wastewater Treatment Plant.
Project timeline
June 2024
Issue notice of commencement
October 2024
Finish preliminary design
February 2025
Finish detailed design
April 2025
Issue tender to contractors
January 2026
Start construction
July 2026
Finish construction
Contact
Robert Stret, P.Eng. PMP
Project Manager, Water and Wastewater Engineering
Niagara Region
905-980-6000 ext. 3190
Email Robert Stret
Patrick Moskwa
Project Manager
Robinson Consultants
905-304-0080 ext. 225
pmoskwa@rcii.com