Niagara Falls Wastewater Treatment Plant Upgrades
All Niagara Region projects
About the project
Niagara Region has undertaken improvements for the Niagara Falls Wastewater Treatment Plant located at 3450 Stanley Ave. in Niagara Falls. The plant is a key asset within our wastewater infrastructure system. It serves about 107,000 residents and visitors throughout the year.
These improvements will ensure increased treatment performance, greater equipment reliability and improved ability to protect the environment by meeting provincial and federal requirements.
The project will consist of three phases.
-
Phase 1: Secondary treatment upgrades
Design of Phase 1 has been completed. Construction is scheduled for completion in June 2026 and includes:
- Various improvements to grit, chemical and secondary clarifier systems
- Replacement of the existing rotating biological contactors with moving bed biofilm reactors
- Construction of new chemical and blower buildings
- Construction of a new chlorine contact tank and dechlorination system
- Improvements to plant access and electrical and water supplies
-
Phase 2: Primary treatment upgrades
Design of Phase 2 is in progress. Design is estimated to be complete Q1 2027 and construction is estimated to begin Q2 2027. This phase is expected to include:
- Structural improvements to the primary clarifier tanks
- Replacement of the primary clarifier sludge removal systems
- Electrical and HVAC upgrades to meet current code requirements
-
Phase 3: Raw sewage pumps and screen upgrades
Design of Phase 3 has not started yet. The project is currently in the initial stages of feasibility study planning. Design details and construction timing are to be determined. This phase is expected to include:
- A new raw sewage screening process
- Upgrade to the raw sewage pumping station
Project timeline
September 2019 to September 2021 - Complete
Phase 1:
Design secondary treatment upgrades
February 2023 to June 2026 - In progress
Phase 1:
Construct secondary treatment upgrades
March 2026 to January 2027 - In progress
Phase 2: Design primary treatment upgrades
April 2027 to February 2029 - following Phase 2 design
Phase 2: Construct primary treatment upgrades
to be determined - following Phase 2
Phase 3: Design and construct raw sewage pump and screen upgrades
Contact
Michelle Miller, C.E.T.
Manager of Capital Projects
Niagara Region
905-980-6000 ext. 3737
Email Michelle Miller
Horia Ispas, P.Eng., PMP
Phase 1 Consultant Project Manager
Environmental Infrastructure Solutions Inc.
Truman Wu, P.Eng., PMP, MBA
Phase 2 Consultant Project Manager
Stantec Consulting Ltd.