Niagara Region, in partnership with the Town of Grimsby, the Town of Lincoln and the Township of West Lincoln, are preparing a Pollution Prevention and Control Plan as well as a Wastewater Master Servicing Plan update study.
The project's scope is to update the previous 2009 Baker Rd. Wastewater Treatment Plant Pollution Control Plan to meet the goals of the procedure F-5-5 and under the Class Environmental Assessment process for Master Plans, develop a prioritized action plan for improvements of the system supporting short and long-term growth and sustainability of the wastewater infrastructure.
This study will satisfy Phase 1 and 2 of the Municipal Engineers Association Class Environmental process (October 2000, as amended in 2007, 2011 and 2015). This is an approved process under the Ontario Environmental Assessment Act and will evaluate alternatives to help support the long-term sustainability of the wastewater systems.
july 2019 - completed
Request for proposal issued
oct. 2019 - completed
Kick-off meeting
nov. 18, 2019 - completed
Technical memo #1 - background review
dec. 2, 2019 - completed
Technical memo #2 - flow monitoring program review, assessment and analysis
feb. 11, 2020 - completed
Technical memo #3 - hydraulic sewer model review and recommendations
feb. 11, 2020 - completed
Technical memo #4 - gap analysis
sept. 25, 2020 - completed
Technical memo #5A - hydraulic modeling development
oct. 2, 2020 - completed
Technical memo #5B - flow monitoring stretch of time in two municipalities
nov. 2, 2020
Technical memo #5C - baseline system performance and growth analysis
nov. 9, 2020
Technical memo #6A - evaluation criteria
dec. 18, 2020
Review of evaluation criteria
Q1 2021
Individual workshops with Grimsby, Lincoln and West Lincoln
May 2021
Preliminary growth data with Planning and Development
July 2021
Workshops with Grimsby, Lincoln and West Lincoln - planning for growth
Aug. 25 - Sept. 8, 2021 - completed
Public Information Centre #1
September 2021 - completed
Draft Pollution Prevention and Control Plan Report
December 2021 - Completed
Notice of completion issued
Ilija Stetic, B.Sc, PMP
Project Manager
905-980-6000 ext. 3777
Email Ilija Stetic
The final report is available for review from Dec. 17 to Jan. 30.
Residents are invited to submit their comments to Ilija Stetic, Project Manager. Email Ilija Stetic.
Final report
Public Information Centre #1 - Aug. 25 to Sept. 8